Schedule for Denny Park

Phase 1 - play area and park lighting
Phase 2 - central water feature and gathering space
Phase 3 - walkways, entrances, and furnishings
Phase 4 - history element, irrigation, and planting

Planning

Events

Dates

Awarded Neighborhood Matching Fund ($15,000)

June 2006

Consultant Selected

July 2006

Schematic Design & Outreach

Events

Dates

Fundraising

Ongoing

Public Meeting #1

August 24, 2006

Public Meeting #2

September 21, 2006

Design Commission

October 2006

Public Meeting #3

November 16, 2006

Park Board

December 2006

City Council presentation

January 2007

Design Development, Documents, Construction, & Fundraising

Events

Dates

NMF money available

September 2007

Large Project Fund application

April, 2007

Kick off party in the Park !!

Summer 2007

Design Development

Nov 07 - Jan 2008

Fundraising

Ongoing

Construction Documents

Feb - April 2008

Starbucks neighborhood grant app

April 2008

Construction Starts (Phase 1)

May 2008

Park reopening celebration

September 2008